Bushfire Clean-up: Status and Schedule
|
Adelaide Hills |
Kangaroo Island |
Yorke Peninsula |
South East |
Total
|
Area affected |
23,295 |
201,830 |
6,606 |
22,893 |
254,624 |
Houses affected |
99 |
135 |
8 |
1 |
243 |
Outbuildings affected |
286 |
200 |
14 |
4 |
504 |
Houses with asbestos |
49 |
92 |
7 |
1 |
149 |
Properties with CCA |
300 |
111 |
5 |
0 |
416 |
Properties cleared |
298 |
235 |
6 |
2 |
541 |
Money committed |
$3,680,815 |
$ 9,948,026 |
$1,467,477 |
$15,096,318 |
|
Waste volume managed |
16,760 t |
31,605 t |
TBC |
TBC |
~ 50,000 t |
Adelaide Hills clean-up schedule
Adelaide Hills waste management clean-up | |
Total clean-up completed | 298 |
Properties with other debris clean-up in progress | 4 |
Money committed for waste management clean-up | $3,680,815
|
Download Adelaide Hills Map here: No items found.
Kangaroo Island clean-up schedule
Kangaroo Island waste management clean-up | |
Total clean-up completed
|
235 |
Properties with other debris clean-up in progress
|
0 |
Money committed for waste management clean-up | $9,948,026
|
Download Kangaroo Island Map here: No items found.
Copies of the schedule can also be viewed at the following locations:
Adelaide Hills
- Lobethal Recovery Centre
- Adelaide Hills Council Civic Centre
- Mt Barker District Council Civic Centre
Kangaroo Island
- Parndana Recovery Centre
- Kangaroo Island Council, Kingscote